This includes the Subansiri Lower project in Arunachal Pradesh (Rs 14,962.2 crore cost overrun), Himachal Pradesh’s Parbati project (Rs 7,215 crore) and Tapovan-Vishnugad (Rs 4,124.5 crore) in Uttarakhand. The data covered projects of Rs 150 crore or more.
Other cost overrun projects such as the Tehri Pumped Storage Plant (Rs 3,168.6 crore) are expected to play a role in improved system reliability by supporting the grid during off-peak hours. The Vishnugad Pipalkoti project (Rs 1,368.8 crore) in Uttarakhand implemented by the Tehri Hydro Development Corporation seeks to increase electricity supply through renewable sources.
At least a dozen hydroelectric projects are facing delays ranging from a few months to fifteen years; though not all have yet reported cost overruns.
A few reasons for time overruns were attributed to disputes with local villagers and delay in finalising agreements.
While the analysis looked at hydropower projects, data also showed that as of March 2023, 54 out of 78 power projects overall are delayed.
GIPHY App Key not set. Please check settings